Construction project of Old Age Home, Chauntra, HP – 175032 October 2023

INTRODUCTION:

From 1th Oct to 4th Nov 2023, Site report and conducted a site assessment of a 2-story building located at the old age home in Chauntra. During these months site supervision with the old age home. At site labour are working seven days a week from 8:00am to 6:00pm.

SITE CONDITIONS:

Our findings from site supervision are described below. Site photo on 01st Oct, 2023 (fig.1) and site photo on 04th Nov, 2023 (fig.2). For curing the plaster water is the most important element. To have batter result as we request, they appointed a person on duty to water all the building from 8:00am to 6:00pm.

Plumbing:

They have finished plumbing the layout and only the accessory fitting is remaining.

Flooring:

They finished the ground and first floor bathroom wall and floor tiles. Room which has synthetic wooden floor will be layer after paint work is done.

Plaster:

They finished plastering.

Roof:

They finished the instructions.

Rainwater Harvesting Tank:

They finished construction of rainwater harvesting tank.

Storeroom:

They have finished constructing the storeroom and painting will start soon (Fig.3).

Wiring:

They have finished the main waring layout at first and ground floor. Only the fittings are remaining to install (Fig.4).

Door and Window:

They finished the installation of door and Jali at first and ground floor. Only the windows are remaining to install. (Fig.5)

Site Development:

They have finished constructing retaining walls around road and water drainages system. They start to extension of boundary wall (Fig.6) and Open-air theater (Fig.7).

Site Activities:

Site visit from Fenesta to measure the window on 18th Oct, 2023. Site visit from CTA on 26th Oct 2023. (Fig.8).

Fig 1 Front façade on 1st Oct 2023
Fig 2- front façade on 4th Nov,2023
Fig 3 - Storeroom
Fig 4 - Wiring
Fig 5 - Wooden Door
Fig 6 - Extension of boundary wall
Fig 7 - Open Air Theater Retaining walls
Fig 8 - Site visit from CTA
Fig 9 - False Ceiling paint
Fig 10 - Leveling pathway to pray wheels
Fig 11 - Stairs
Fig 12 - Exterior wall painting

LIMITATION OF INVESTIGATION:

This report was prepared with information gathered from inspections during construction. As-built drawings and original construction blueprints were made available to us. Construction blueprint, materials, structural analysis of the building were used for this report.