Project title: Miao New Hall Construction
Total Cost of Project: 14,920,681/- (Rupees One Hundred Forty-Nine Lakh Twenty Thousand Six Hundred Eighty-One only)
Project Location: Miao Tibetan Settlement, Arunachal Pradesh
Funded by: TAWS, CTA Dharamshala
Start of the project: 21st August 2023
End of the project: 20th November 2024
Status: Ongoing
PROJECT DESCRIPTION & PROGRESS:
The proposal for constructing a new hall in Miao Tibetan Settlement arose from the limitations of the existing hall, which proved insufficient to accommodate the growing population of the settlements. During large gatherings, many individuals were forced to remain outside due to the hall’s limited capacity. Additionally, the deteriorating condition of the current hall, coupled with constraints on expansion due to limited available space, underscored the necessity for a new, larger, and more spacious facility for the community.
With a total budget of INR 14,920,681 approved for the construction, a tender call was initiated, ultimately awarding the contract to Choepheling Tibetan Service Co-operative Society ltd (CTSCS). The contract was officially signed on 21st August 2023, with expectations set for completion by 20th November 2024. This new hall promises to address the pressing needs of the settlements, providing ample spaces for gathering and improved infrastructure for the community.