Project title: Tezu Staff quarter construction
Total Cost of Project: 61, 67,600/- (Rupees Sixty One Lakh Sixty Seven Thousand Six Hundred only)
Project Location: Tezu Tibetan Settlement, Arunachal Pradesh
Funded by: TAWS, CTA Dharamshala
Start of the project: 24th May, 2023
End of the project: 30th October, 2024
Status: completed
PROJECT DESCRIPTION & PROGRESS:
The Tezu Staff quarter, constructed a long time ago, has been steadily deteriorating due to the harsh monsoon and humid conditions prevalent in the area. Inside, the rooms were not spacious enough, and visible signs of wear and tear adorned the walls. A total budget of INR 61, 67,600 was proposed and subsequently approved.
The contract for this construction project was awarded to Mr. Nazim Uddin, with the agreement signed on 24th May, 2023. New constructed staff quarter now offers significantly improved living conditions, addressing the structural deficiencies and enhancing the overall functionality of the facility.