Project Completion Report: Renovation of the Tibetan Settlement Office and Staff Quarters, Shillong.
Project Title: Renovation of the Tibetan Settlement Office and Staff Quarters, Shillong.
Project Location: Sambhota Tibetan School, Upper Shillong
Total Cost of Project: ₹6,09,816/- (Rupees Six Lakh Nine Thousand Eight Hundred Sixteen only)
Funded by: TAWS, CTA
Work Period: 4th August, 2025 to 30th September, 2025
Project Progress and Description
Earlier, the Tibetan Settlement Office (TSO), Shillong was functioning from a rented premises at Lower Lachumiere, East Khasi Hills District, with limited public access and high rental costs.
To address these issues, part of the boy’s hostel at Sambhota Tibetan School, Upper Shillong was converted into office space and staff quarters. The office area was partitioned into two cabins for the Tibetan Settlement Officer and the Office Secretary. Staff quarters and the Secretary’s residence were also created using existing buildings.
All civil, electrical, and painting works were completed within two months. The Tibetan Settlement Office was officially shifted to Sambhota Tibetan School, Upper Shillong on 3rd October 2025.
This project was funded by the Tibetan Association Welfare Society (TAWS), CTA, Dharamsala. We sincerely express our gratitude for their generous support.